A ventilation duct that collides with a beam. A cable tray installed exactly where the plumbing was due to run. On a building site, these conflicts are often discovered at the worst possible moment – when contractors are already on site and every rework costs days. Clash detection is designed precisely to identify them beforehand, on screen.

What is clash detection?

In French, it is referred to as ‘collision detection’ or ‘conflict checking’. The principle is simple. The 3D models from the various disciplines are overlaid, and the software then flags up every point where two elements interfere with one another.

There are generally two types of conflict.

  • Physical conflicts, where two elements occupy the same space, such as a pipe passing through a load-bearing wall without a recess
  • Space conflicts, where nothing touches but there is insufficient space – for example, for insulating a pipe, accessing a valve or maintaining a monobloc

The latter are often the most costly. Invisible on a 2D plan, they sometimes only become apparent upon commissioning or during the first maintenance visit.

As regards recesses, the SIA 410/1 and 410/2 guidelines also specify how existing installations and recesses should be shown.

How does an inspection take place?

Firstly, each design consultancy produces its own model. These models are then assembled into a coordination model, which requires a common reference point. The City of Bern, for example, requires a reference point based on the MN95 national coordinate system and the correct elevation, so that all specialised models align exactly at the same location.

Next comes the configuration. Decisions are made as to which disciplines to compare with one another, and with what tolerances. A pipe that comes within two millimetres of a suspended ceiling is not as serious an issue as a duct passing through a floor slab. Without rules, the software identifies thousands of conflicts, many of which are of no significance.

Finally, the selected conflicts are assigned, discussed and resolved during a coordination meeting. The BCF format allows each comment to be linked to the relevant element in the model, along with a screenshot and a designated person responsible.

What Swiss project owners are asking for

In Switzerland, this requirement is already included in the specifications. The KBOB document on the application of the BIM method in the building sector thus provides for a BIM coordination plan.

The City of Bern goes a step further. In its information exchange requirements model, proof that there are no clashes is one of the use cases required of contractors. Overlaps between elements must be detected and corrected during coordination meetings, with a final check carried out before the end of each phase. Contractors submit PDF reports listing each clash, complete with a description and a screenshot. Furthermore, any solution that affects the building’s functionality – such as a loss of usable floor area or a relocated fixture – must be approved by the City.

Practitioners draw the same conclusion. In an interview published by espazium, building services engineers suggest that a selection of conflict points should be addressed as early as the preliminary design stage.

In renovation projects, everything depends on the existing building’s layout

In a new-build, all models come from the design offices. In an existing building, however, the building itself becomes a key factor in the project. Its beams, slab overhangs, old service ducts and suspended ceilings impose constraints that nobody has recently drawn up. The City of Bern also requires that each element in the model be marked as either existing or new.

A 3D laser scanner mounted on a tripod, scanning an open suspended ceiling with ducts and beams in a building undergoing renovation

If the model of the existing structure is based on archived plans, conflict detection becomes meaningless. The software may report zero conflicts, whilst in reality the beam is twelve centimetres lower than shown on the plan. The problem then resurfaces on site, as if nothing had been checked.

This is where 3D surveying changes the game. A laser scan of suspended ceilings, service ducts and plant rooms provides an accurate point cloud of the existing structure, which can be utilised in two ways.

  • Modelling the existing structure in BIM, to the level of detail required for the project, then integrating it into the coordination model
  • Directly comparing the new services with the point cloud to verify that they fit within the space actually available

In both cases, the accuracy of the survey is defined in advance. Our articles on 3D scanning for HVAC surveys, the level of detail in BIM in Switzerland and the accuracy of a 3D survey explain these choices in more detail.

Errors that render detection pointless

  • Starting the check too late, when decisions have already been finalised
  • Overlooking tolerances and getting bogged down in thousands of insignificant clashes
  • Working with poorly aligned models, which create false clashes
  • Modelling the existing structure based on plans that have never been verified on site
  • Failing to appoint anyone to oversee the resolution of conflicts

Implementing an effective approach

  1. Specify in the specifications who coordinates, at what intervals and according to which rules
  2. Align all models to the same reference point
  3. Set tolerances and clearance distances by discipline
  4. In an existing building, have the service areas surveyed before drawing up the new service networks
  5. Prioritise and resolve conflicts, and document each decision

In conclusion

Clash detection shifts the identification of problems from the construction site to the office, where corrections can be made within the model rather than with a grinder. However, it is only as good as the models being compared. In renovation projects, everything therefore begins with a reliable survey of the existing structure.